注水站工程竣工决算管理评价体系研究

开篇:润墨网以专业的文秘视角,为您筛选了一篇注水站工程竣工决算管理评价体系研究范文,如需获取更多写作素材,在线客服老师一对一协助。欢迎您的阅读与分享!

摘要:工程竣工决算管理属于多阶段、多主体、动态化的系统性工作。本文针对注水工程竣工决算管理中各项评价指标,利用层次分析法与模糊数学法计算整个体系的权重值与评价分值。评价体系的的定量化可以客观真实的反应出此注水站工程竣工决算管理水平的优劣,从而有针对的进行改善,最终降低工程造价,提高投资收益。

Abstract: Project completion accounting management belongs to multi-stage, multi-subject and dynamic systemic work. Aiming at each evaluation index in water injection station project completion accounting management, using the analytic hierarchy process and fuzzy mathematics method, the weight value and the evaluation score of the whole system is calculated. The quantitative evaluation system can objectively reflect the management level of water injection station project completion accounting, thus targeted improvements can be done, and eventually the project cost can be reduced and investment returns improved.

关键词:竣工决算;模糊数学法;层次分析法;管理评价

Key words: completion accounting;fuzzy math method;analytic hierarchy process;management evaluation

中图分类号:F812.3 文献标识码:A 文章编号:1006-4311(2016)24-0058-02

0 引言

注水站工程存在投资大、周期长、决算复杂等特性,由于其建设主要是以竣工决算的形式来反映工程的实际资产,因此注水站程竣工决算的管理对整个企业各项工程的建设有着重大的影响。但在实际的竣工决算过程中,存在财务、组织、决算人员素质以及资料信息收集等方面的问题,使得竣工决算往往与实际情况不相符,延长油田现有的评价体系却不足以对竣工决算的管理水平进行客观的评价进行改进[1]。本文主要将层次分析法与模糊数学法综合使用,建立模糊层次评价体系,定量的计算出延长油田南泥湾注水站工程竣工决算的管理水平,验证此评价方法的可行性,并进一步在整个延长油田进行推广。

1 建立评价体系

在进行延长油田南泥湾注水站工程竣工决算的管理评价时,首先需要建立相应的评价体系。根据层次分析法,南泥湾注水站工程竣工决算管理作为一个整体的评价体系,可以分为三个指标层。第一层为南泥湾注水站工程竣工决算管理评价体系的集合,为A;第二层为集合A所含的指标层Ai;第三层为各个指标层Ai所含的指标因素Ni。南泥湾注水站工程竣工决算管理评价体系的建立如下所示[2]:

财务管理A1={财务监督N1、费用控制N2、抵押金保管N3};

组织管理A2={项目批复情况N4、政策问题N5、部门沟通情况N6};

信息收集A3={进度汇报N7,资料提交N8};

人员素质A4={结算水平N9,综合能力N10}。

其后利用层次分析法构建南泥湾注水站工程竣工决算评价级别,通常将评分体系分为五个等级,用V表示,则有:V={高、较高、一般、较低、低},其具体评分表见表1。

2 计算评价体系权重

完成南泥湾注水站工程竣工决算管理指标体系的建立之后,需要对各指标因素之间的关联系数进行判断,利用5分制表示,1、2、3、4、5分别表示重要性相同、后者稍微重要、后者比较重要、后者特别重要、后者极端重要,反之则用1、1/2、1/3、1/4、1/5。依据此权重值的打分,可建立延长油田南泥湾注水站工程竣工结算管理体系A以及各项评价因素Ai的权重关联性,用矩阵U表示[3]。